Archive for August 2nd, 2006

Expansion of ADSL capacity

Posted: Wednesday, August 2nd, 2006 at 17:52 by Neil Watson

We are pleased to announce that on Thursday 03rd August 2006 we will be introducing three additional LNS servers into our Global Switch facility. These additional servers will increase the total numbers of users allowed to connect by approximately 15000, providing future growth potential for Entanet and all of our partners. The servers will initially be configured to reside outside of our live environment and, as such, the introduction will not affect any live service and no down time is envisaged. The extra capacity will be introduced on a gradual basis as required.

Power Ugrade to Telford Headquarters

Posted: Wednesday, August 2nd, 2006 at 10:57 by Neil Watson
Date: 04th August 2006

This coming Friday we will be undertaking an upgrade to our HQ power supply in order to provide extra capacity and growth for our datacentres. The work will require the removal of mains power to and as such, we will switch to our standby generators to ensure continuity of service. We do not envisage downtime for any customer. All work should be completed by 13.00hrs.

  1. Neil Watson says:

    We are pleased to inform you that all work has now been completed with no unplanned effects.

Telford Datacentre Power Issue – 1st August 2006

Posted: Wednesday, August 2nd, 2006 at 09:43 by Neil Watson

Following on from the minor power issue experienced on 01st August 2006, please see attached incident report for information. The outage affected a small percentage of customers and a reoccurrence is not envisaged.

Reason for Outage report – 01st August 2006