Stafford Park Power Works

Posted: Wednesday, September 20th, 2006 at 10:14 by Neil Watson

01st October 2006 08.00 – 16.00hrs

We have been advised by our mains electricity supplier that there will be a power outage across the Stafford Park area of Telford on 01st October 2006 between the hours of 08.00 – 16.00. This work is being completed to increase power supply resilience in the area. All services supplied from, or located in, our Telford HQ datacentres will be affected switching to UPS and backup power as required.

Our backup generators will automatically take over the generation and supply of power during the power outage. We have sufficient fuel to service this time period, and have also secured additional fuel on short notice should it be required for any reason. We will also be arranging a test of the automatic switchover before the date of the planned work and will advise according once the details have been finalised.

One Response to “Stafford Park Power Works”

  1. Neil Watson says:

    The failover test has now be scheduled for the 23rd September 2006 at 07.00hrs. We will have engineers on site during the test and currently forsee no problems.