Archive for June 5th, 2007

Telford Data Centre 3

Posted: Tuesday, June 5th, 2007 at 17:46 by Neil Watson

We are currently experiencing an issue with hosting in Data Centre 3 in Telford. Initial investigations indicate that power to the rack containing the main router for the data centre has tripped and our engineers are currently working to re-establish the power and hence restore sevice. We will update further as more information is available.

  1. Neil Watson says:

    Power to the rack has know been restored. An incident report will be prepared and will be posted as soon as possible.

  2. Neil Watson says:

    The incident report for this outage is now available:

    Incident Report: DC3 Routing

New LNS Routers

Posted: Tuesday, June 5th, 2007 at 11:38 by Steve Lalonde

All the new LNS routers are now live

LNS to Central Map (05-06-2007)

  • Central 1: ironwood, jujuba, katsura
  • Central 2: birch, chestnut, dogwood
  • Central 3: elm, fir, larch
  • Central 4: poplar, redwood, spruce
  • Central 5: maple, nutmeg, oak

if you are still connected to dogwood or larch from before this post you may not be on the central listed.

for the latest LNS maping please see
http://noc.enta.net/?page_id=166