Planned Maintenance: Installation of new core routers.

Posted: Tuesday, September 24th, 2013 at 10:34 by Steve Lalonde

0:01 – 06:00 Friday 4th October 2013

During the above window we will be installing additional core routers in both Telehouse East and Telehouse North

The new routers will be connected to the existing routers and several core links will be moved to the new routers. Where a core link is being moved traffic will be switched to alternate paths before the link is moved.

No customer circuits will be moved during this work and no downtime is expected.

Tags: , , , , ,

2 Responses to “Planned Maintenance: Installation of new core routers.”

  1. Steve Lalonde says:

    Corrected Month to October

  2. Steve Lalonde says:

    This maintenance is now complete.