Emergency Work: Telford UPS

Posted: Thursday, August 13th, 2015 at 13:05 by Mark Yardley

We have experienced a failure of one of the UPS devices that protects telford-dc3.core. We will shortly be undertaking work to replace the failed unit and restore full power redundancy. Services connected to or through telford-dc3.core should be considered at risk until the work is completed.

Further updates will be provided within the hour.

Tags: , ,

2 Responses to “Emergency Work: Telford UPS”

  1. Mark Yardley says:

    Engineers are currently progressing with the work. Further updates will follow shortly.

  2. Mark Yardley says:

    The work is now complete and UPS redundancy has been restored.