Planned work: Legacy VoIP platform

Posted: Friday, February 9th, 2018 at 16:14 by David Derrick

Monday 19 February 2018 22:00-23:59 GMT

During the above window we will be relocating some servers within our Telford datacentre. Where possible servers will be removed from active pools in advance to minimise disruption but some calls might disconnect if they are still in progress.

  1. Richard Partridge says:

    This maintenance work has now begun.

  2. Jamie Smith says:

    This work has now been completed.

Planned Maintenance: Columbo.core

Posted: Friday, February 9th, 2018 at 16:11 by Jamie Smith

Tuesday 13th February 23:50 – Wednesday 14th February 01:00

During the above window, we will be carrying out planned work on one of the bearer links into Columbo.core. This bearer link provides leased line connectivity for a small number of BT circuits. No down time is expected, however circuits which reside on this bearer will be notified individually.

  1. Jamie Smith says:

    This work has now been completed