At Risk: Planned Core Maintenance

Posted: Friday, March 9th, 2018 at 15:57 by Ming-Yu Hsieh

Thursday 15th March 2018 20:00 – 23:00

During the above maintenance window, we will be undertaking work on the core network.

No down time is expected and all precautions will be taken to avoid any disruption, however during this window routing may take different paths than usual.

  1. Ming-Yu Hsieh says:

    This work has now been completed.

Planned Maintenance: Telford DC1 BT circuit moves

Posted: Friday, March 9th, 2018 at 14:40 by Iain Beveridge

Thursday 15th March 00:00 – 02:00

During the above window we will be moving all 1Gbps BT EAD circuits that are directly connected into our Telford DC2 core into Telford DC3 core. Our support team are in the process of contacting any customers that will be moved. Circuits will be switched over one by one and although there is a 2 hour window, downtime for each circuit is anticipated to be less than 5 minutes.

  1. Jamie Smith says:

    This work has now been completed.