Planned Maintenance: Telford-dc3-2.core

Posted: Monday, April 23rd, 2018 at 17:41 by Gurinder Bansal

Wednesday 2nd May 2018 00:01 – 06:00

During the above window we will be replacing telford-dc3-2.core.enta.net with a higher capacity router.

All services currently terminated in this location will be migrated on to the new hardware. This includes leased-lines, colocation and pseudowires terminating at this location. Whilst actual downtime is expected to be no more than 30 minutes for each circuit, the full 6 hrs may be required to account for any unforeseen issues.

All other traffic that would normally route through this location will take alternative paths.

  1. Mark Yardley says:

    This work is now complete.

Planned Maintenance: birmingham-te.core.enta.net

Posted: Monday, April 23rd, 2018 at 09:48 by Gurinder Bansal

Friday 27th April 2018 00:01-06:00

During the above maintenance window, we will be installing additional core equipment as part of ongoing network expansion.

All services currently terminated in this location will be migrated on to the new hardware. This includes all DSL, EWCS, leased lines and wholesale circuits at this location. Whilst actual downtime is expected to be no more than 20 minutes for each circuit, the full 6 hrs may be required to account for any unforeseen issues.

All other traffic that would normally route through this location will not be affected.

  1. Gurinder Bansal says:

    This work is now complete