Archive for July 4th, 2018

Planned Work: Peterborough.core

Posted: Wednesday, July 4th, 2018 at 16:14 by Richard Partridge

Tuesday 10th July 00:01 – 06:00

During the above window we will be commissioning new equipment into the Peterborough POP.  The work will require routing adjustments with one of our transit providers. The work is not expected to result in any downtime however the core should be considered at risk for the duration of the window whilst changes are taking place.

Planned Maintenance: Telehouse-east4

Posted: Wednesday, July 4th, 2018 at 11:33 by Gurinder Bansal

Thursday 12th July 2018 00:01 – 06:00

During the above window we will be completing a planned maintenance to upgrade standby hardware within telehouse-east4.core. Broadband traffic will be steered away from Entanet’s DSL platform in Telehouse to Interxion. Although no downtime is expected during this maintenance window, all other services should be considered at-risk.

  1. Gurinder Bansal says:

    This work is now complete.