Planned Maintenance: Equinix.core

Posted: Monday, September 17th, 2018 at 17:50 by Gurinder Bansal

Tuesday 25th September 2018 00:01 – 06:00

During the above windows we will be completing planned maintenance to upgrade our core equipment, equinix.core.enta.net.

We expect all services currently terminated in this location to have a maximum downtime of 1 hour. Services include Transit, EWCS, Leased lines, Co-location, Wholesale handoff and Pseudowires. Whilst actual downtime is expected to be no more than 1 hour, the full 6 hours may be required to account for any unforeseen issues. All other traffic that would normally route through this location will take alternative paths.

Tags: , ,

2 Responses to “Planned Maintenance: Equinix.core”

  1. Gurinder Bansal says:

    This work is now commencing.

  2. Gurinder Bansal says:

    This work is now complete.

Leave a Reply

You must be logged in to post a comment.