Wednesday 5th December 2018 00:01 – 06:00

During the above window we will be replacing Glasgow.core.enta.net with a higher capacity router.

We expect all services currently terminated in this location to have a maximum downtime of 1 hour. Services include: Leased lines, DSL, EWCS, Wholesale handoff and Pseudowires. Whilst actual downtime is expected to be no more than 1 hour, the full 6 hours may be required to account for any unforeseen issues.

All other traffic that would normally route through this location will take alternative paths.

Tags: , ,

2 Responses to “Planned Maintenance: Glasgow.core”

  1. Gurinder Bansal says:

    This work is now commencing.

  2. Gurinder Bansal says:

    This work is now complete.