At Risk: Peterborough BT POP

Posted: Tuesday, April 2nd, 2019 at 15:52 by Iain Beveridge

Monday 8th April 2019, 23:45 – Tuesday 9th April 2019, 02:00.

After a power check within Peterborough POP, BT identified an issue with part of their infrastructure. BT will undertake work in the above window to replace isolator cables to a power supply board. The supply board provides the A-Feed, generator backed supply to several racks within the MUA including Entanet’s. An Entanet engineer will be on site for the duration of the maintenance to ensure power to our racks is maintained via the unaffected B-Feed.

No downtime is expected however all directly connected services should be considered at risk.

One Response to “At Risk: Peterborough BT POP”

  1. This work is now complete.