Archive for the ‘At-Risk’ Category

Planned Work: Faraday TE

Posted: Tuesday, November 24th, 2020 at 16:52 by Iain Beveridge

Thursday 10th December 2020, 21:00 – Friday 11th December 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, The above TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment may experience a small period of downtime.

Planned Work: Manchester TE

Posted: Tuesday, November 24th, 2020 at 13:01 by Iain Beveridge

Thursday 3rd December 2020, 21:00 – Friday 4th December 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, The above TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment may experience a small period of downtime.

Planned Work: Columbo TE

Posted: Wednesday, November 11th, 2020 at 12:21 by Iain Beveridge

Thursday 26th November 2020, 21:00 – Friday 27th November 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, The above TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment may experience a small period of downtime.

Planned Work: Glasgow TE

Posted: Wednesday, November 11th, 2020 at 12:15 by Iain Beveridge

Thursday 19th November 2020, 21:00 – Friday 20th November 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, The above TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment may experience a small period of downtime.

At Risk: Virgin Media Circuits

Posted: Wednesday, November 4th, 2020 at 16:29 by Iain Beveridge

Friday 6th of November 20:00 – Monday 9th November 06:00

During the above window as small number of circuits provided to us by Virgin Media are at risk while Virgin conduct work to resplice a section of fibre due to a location closure. No circuit will be down for the entirety of the window and any that are effected are estimated to only be down for 30 minutes to a maximum of 4 hours.

Planned Work: Bristol TE

Posted: Tuesday, October 27th, 2020 at 15:44 by Iain Beveridge

Thursday 12th November 2020, 21:00 – Friday 13th November 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Bristol TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment may experience a small period of downtime.

Planned Work: Stepney Green

Posted: Tuesday, October 27th, 2020 at 15:43 by Iain Beveridge

Thursday 05th November 2020, 21:00 – Friday 06th November 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Stepney TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

  1. Naz says:

    work is now commencing

  2. Naz says:

    Work has been completed

Planned Work: Preston Core

Posted: Tuesday, October 6th, 2020 at 14:29 by Iain Beveridge

Thursday 22nd October 2020, 21:00 – Friday 23rd October 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Preston TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

  1. Naz says:

    Work is now commencing

  2. Naz says:

    Work has been completed successfully

Planned Work: Peterborough TE

Posted: Wednesday, September 9th, 2020 at 08:41 by Iain Beveridge

Thursday 8th October 2020, 21:00 – Friday 9th October 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Peterborough TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

Planned Work: Milton Keynes POP

Posted: Wednesday, August 26th, 2020 at 09:59 by Iain Beveridge

Thursday 24th September 2020, 21:00 – Friday 25th September 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Milton Keynes TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.