Posts Tagged ‘Planned’

Planned Maintenance: Interxion & Telehouse East

Posted: Tuesday, November 13th, 2018 at 11:49 by Gurinder Bansal

Wednesday 21st November 2018 00:00 – 06:00

During the above window we will be completing a planned maintenance to upgrade hardware within telehouse-east4.core & Interxion3.core. No downtime is expected and all precautions will be taken to avoid any disruption, however during this window both sites should be considered at risk.

Planned Maintenance: Telford

Posted: Wednesday, October 17th, 2018 at 11:41 by Mark Yardley

Wednesday 24th October 20:00 – 23:59

During the above window we will be performing cable management on equipment servicing Openreach leased line circuits terminating in our Telford location. Although this work is anticipated to cause no down time for services they should be considered at risk for the duration the window.

  1. Mark Yardley says:

    This work is now complete.

Planned Maintenance: LD8/Telecity-Hex89

Posted: Tuesday, September 25th, 2018 at 11:33 by Mark Yardley

Tuesday 2nd October 2018 00:01 – 06:00

During the above window we will be replacing telecity-hex89.core with a higher capacity router.

We expect all services currently terminated in this location to have a maximum downtime of 1 hour. Services include Transit, EWCS, Leased lines, Wholesale handoff and Pseudowires. Whilst actual downtime is expected to be no more than 1 hour, the full 6 hours may be required to account for any unforeseen issues. All other traffic that would normally route through this location will take alternative paths.

  1. Gurinder Bansal says:

    This work is now commencing.

  2. Gurinder Bansal says:

    This work is now complete.

Planned Maintenance: Manchester

Posted: Tuesday, September 18th, 2018 at 14:35 by Gurinder Bansal

Thursday 27th September 2018 00:01 – 06:00

During the above window we will be replacing man.core.enta.net with a higher capacity router.

We expect all services currently terminated in this location to have a maximum downtime of 1 hour. Services include Transit, EWCS, Leased lines, Wholesale handoff and Pseudowires. Whilst actual downtime is expected to be no more than 1 hour, the full 6 hours may be required to account for any unforeseen issues. All other traffic that would normally route through this location will take alternative paths.

  1. Gurinder Bansal says:

    This work is now commencing.

  2. Gurinder Bansal says:

    This work is now complete.

Planned Maintenance: Equinix.core

Posted: Monday, September 17th, 2018 at 17:50 by Gurinder Bansal

Tuesday 25th September 2018 00:01 – 06:00

During the above windows we will be completing planned maintenance to upgrade our core equipment, equinix.core.enta.net.

We expect all services currently terminated in this location to have a maximum downtime of 1 hour. Services include Transit, EWCS, Leased lines, Co-location, Wholesale handoff and Pseudowires. Whilst actual downtime is expected to be no more than 1 hour, the full 6 hours may be required to account for any unforeseen issues. All other traffic that would normally route through this location will take alternative paths.

  1. Gurinder Bansal says:

    This work is now commencing.

  2. Gurinder Bansal says:

    This work is now complete.

Planned Maintenance: Redbus-sov.core

Posted: Monday, September 3rd, 2018 at 17:00 by Gurinder Bansal

Tuesday 11th September 2018 00:01 – 06:00

During the above window we will be replacing redbus-sov.core.enta.net with a higher capacity router.

All services currently terminated in this location will be migrated on to the new hardware. This includes EWCS, Transit, Leased lines and Pseudowires terminating at this location. Whilst actual downtime is expected to be no more than 1 hour, the full 6 hours may be required to account for any unforeseen issues.

All other traffic that would normally route through this location will take alternative paths.

  1. Gurinder Bansal says:

    This work is now commencing.

  2. Gurinder Bansal says:

    This work is now complete.

Planned Maintenance: Interxion2.core

Posted: Thursday, August 30th, 2018 at 17:45 by Gurinder Bansal

Thursday 6th September 2018 00:01 – 06:00

During the above window we will be replacing interxion2.core.enta.net with a higher capacity router.

We expect all services currently terminated in this location to have a maximum downtime of 1 hour. Services include Transit, EWCS, Leased lines, Co-location, Wholesale handoff and Pseudowires. Whilst actual downtime is expected to be no more than 1 hour, the full 6 hours may be required to account for any unforeseen issues.

All other traffic that would normally route through this location will take alternative paths.

  1. Gurinder Bansal says:

    This work is now commencing.

  2. Gurinder Bansal says:

    This work is now complete.

Planned Maintenance: Interxion3.core

Posted: Tuesday, August 21st, 2018 at 11:09 by Gurinder Bansal

Wednesday 29th August 2018 00:01 – 06:00

During the above windows we will be completing planned maintenance to upgrade our core equipment, interxion3.core.enta.net.

We expect all services currently terminated in this location to have a maximum downtime of 1 hour. Services include Transit, EWCS, Leased lines, Co-location, Wholesale handoff and Pseudowires. Whilst actual downtime is expected to be no more than 1 hour, the full 6 hours may be required to account for any unforeseen issues. All other traffic that would normally route through this location will take alternative paths.

Prior to works, broadband traffic will be steered away from Interxion to lessen the customer impact and on successful completion the broadband traffic will be re-balanced between multiple locations.

  1. Gurinder Bansal says:

    This work is now commencing.

  2. Gurinder Bansal says:

    This work is now complete.

Planned Maintenance: Columbo.core

Posted: Monday, July 30th, 2018 at 16:32 by Gurinder Bansal

Tuesday 14th August 2018 00:01 – 06:00

During the above window we will be replacing columbo.core.enta.net with a higher capacity router.

All services currently terminated in this location will be migrated on to the new hardware. This includes DSL, Leased lines and Pseudowires terminating at this location. Whilst actual downtime is expected to be no more than 1 hour, the full 6 hours may be required to account for any unforeseen issues.

All other traffic that would normally route through this location will take alternative paths.

  1. Gurinder Bansal says:

    This work is now commencing.

  2. Gurinder Bansal says:

    This work is now complete.

Planned Maintenance: Telehouse-north.core

Posted: Monday, July 16th, 2018 at 16:40 by Gurinder Bansal

Friday 20th July 00:01 – 06:00

During the above window we will be completing an upgrade to standby hardware within telehouse-north.core. Although no downtime is expected during this maintenance window, all services should be considered at-risk.

  1. Gurinder Bansal says:

    This work is now complete.