Third Party Emergency Work: Vodafone, Sovereign House, London

Posted: December 14th, 2021 at 14:26 by Iain Beveridge

Friday 17th December 2021 22:00 – Saturday 18th December 06:00

During the above window the third-party supplier Vodafone will be carrying out intrusive testing and reloading their network termination equipment. Some customers handed over in Sov House will experience an outage during the maintenance window

We apologise for the short notice and any inconvenience this may cause.

Emergency Works: Birmingham TE

Posted: December 10th, 2021 at 15:50 by Adam Heath

Tuesday 14 December 00:00 – 02:00

CityFibre will be undertaking emergency maintenance work within the above window. This work will require the power feed to be moved on a single fed device.

There is only one device effected by the work, the core network devices should not be affected by this change. However due to the nature of work ongoing in the rack all equipment should be considered at risk.

The customers directly connected into the equipment effected by the work will experience a small period of downtime and should have received communication of this change.

Third Party Emergency Work: Vodafone, Sovereign House, London

Posted: December 7th, 2021 at 16:02 by Iain Beveridge

Wednesday 8th December 2021 01:00 – 05:00

During the above window our third-party Vodafone will be carrying out work swapping their SFPs, cleaning fibres and reloading their equipment. Customers will experience an outage during the maintenance window

We apologise for the short notice and any inconvenience this may cause.

Planned Work: LEC191, NOR340, MK938, PB1353 CB332 LON5, REA282 & SLO2

Posted: December 7th, 2021 at 15:08 by Iain Beveridge

Tuesday 14th December 2021 00:01 – 04:00

We apologise for the short notice and any inconvenience this may cause.

During the above window we will be carrying out work to add additional capacity to our core network links between the following locations LEC191, NOR340, MK938, PB1353 CB332 LON5, REA282 & SLO2 . We do not expect any impact to services during this time. We will be monitoring all traffic closely to ensure the work has been successful.

Planned Work: LEE1957, ROT36, NOT238, DER87, LEC191, REA282, SLO664

Posted: December 7th, 2021 at 15:07 by Iain Beveridge

Friday 10th December 2021 00:01 – 04:00

During the above window we will be carrying out work to add additional capacity to our core network links between the following locations LEE1957, ROT36, NOT238, DER87, LEC191, REA282, SLO664. We do not expect any impact to services during this time. We will be monitoring all traffic closely to ensure the work has been successful.

We apologise for the short notice and any inconvenience this may cause.

Planned Works: LEE1957, LEC191, LON5 & REA282

Posted: December 7th, 2021 at 15:04 by Iain Beveridge

Wednesday 8th December 2021 00:01 – 04:00

During the above window we will be carrying out work to add additional capacity to our core network links between the following locations LEE1957, LEC191, LON5 & REA282 . We do not expect any impact to services during this time. We will be monitoring all traffic closely to ensure the work has been successful.

We apologise for the short notice and any inconvenience this may cause.

Planned Work: LON5 – LEC191

Posted: December 2nd, 2021 at 13:03 by Mark Yardley

Friday 3rd December 2021 00:01 – 03:00

During the above window we will be carrying out work to temporarily bring a core link between LON5 and LEC191 live. We do not expect any impact to services during this time. Please note that all changes well be reverted at the end of the window. We will be monitoring services closely to ensure the work has been successful.

We apologise for the short notice and any inconvenience this may cause.

Planned Work: LON5 – LEC191

Posted: November 24th, 2021 at 09:04 by Iain Beveridge

Thursday 24th November 2021, 00:01 – 06:00

During the above window we will be carrying out work to bring a core link between LON5 and LEC191 live. We do not expect any impact to traffic during this time. We will be monitoring this closely to ensure the work has been successful.

We apologise for the short notice and any inconvenience this may cause.

Planned Works: Gateshead Saltmeadows

Posted: November 16th, 2021 at 10:21 by Adam Heath

2021-11-24 08:00 – 20:00.

During the above window we will be completing non-service affecting maintenance on the mains power feed into this FEx.

This work is not expected to impact any services due to backup power supply in place.

Planned Works: Week 2 – Coventry, Bournemouth & Peterborough

Posted: October 21st, 2021 at 08:49 by Jamie Smith

Wednesday 10/11/2021 08:00 – Friday 12/11/2021 18:00

During the above window we will be completing non-service affecting maintenance on the PDU Racks in the FEx.

This work is not expected to impact any services due to backup power supply in place.