Planned Work: Glasgow TE

Posted: Wednesday, November 11th, 2020 at 12:15 by Iain Beveridge

Thursday 19th November 2020, 21:00 – Friday 20th November 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, The above TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment may experience a small period of downtime.

PLANNED WORKS: London

Posted: Friday, October 30th, 2020 at 22:36 by Adam Heath

Change Summary: Wholesale Ethernet Planned Works Full Outage multiple Sky Circuits.

Type of Change: Planned
Impact: Full outage to service


Start Date: 30/10/2020 00:00:00 GMT
End Date: 31/10/2020 06:00:00 GMT

Start Date: 31/10/2020 00:00:00 GMT
End Date: 01/11/2020 06:00:00 GMT

Start Date: 01/11/2020 00:00:00 GMT
End Date: 02/11/2020 06:00:00 GMT

Reason for work: Maintenance-Third party work

Apologies for any disruption this may cause.

Planned Work: Bristol TE

Posted: Tuesday, October 27th, 2020 at 15:44 by Iain Beveridge

Thursday 12th November 2020, 21:00 – Friday 13th November 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Bristol TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment may experience a small period of downtime.

Planned Work: Stepney Green

Posted: Tuesday, October 27th, 2020 at 15:43 by Iain Beveridge

Thursday 05th November 2020, 21:00 – Friday 06th November 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Stepney TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

  1. Naz says:

    work is now commencing

  2. Naz says:

    Work has been completed

Planned Work: Preston Core

Posted: Tuesday, October 6th, 2020 at 14:29 by Iain Beveridge

Thursday 22nd October 2020, 21:00 – Friday 23rd October 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Preston TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

  1. Naz says:

    Work is now commencing

  2. Naz says:

    Work has been completed successfully

Cancelled: Planned Work: Newcastle TE

Posted: Wednesday, September 9th, 2020 at 11:48 by Iain Beveridge

Wednesday 30th October 2020, 00:01 – Wednesday 30th October 2020, 06:00

During the above window we will be undertaking the move of the core router in Newcastle TE to free up space within the rack. All customers directly connected to the box will receive downtime during this window.

  1. Above will be rescheduled accordingly.

Planned Work: Peterborough TE

Posted: Wednesday, September 9th, 2020 at 08:41 by Iain Beveridge

Thursday 8th October 2020, 21:00 – Friday 9th October 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Peterborough TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

Planned Work: Milton Keynes POP

Posted: Wednesday, August 26th, 2020 at 09:59 by Iain Beveridge

Thursday 24th September 2020, 21:00 – Friday 25th September 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Milton Keynes TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

Planned Work: Wolverhampton POP

Posted: Wednesday, August 19th, 2020 at 15:47 by Iain Beveridge

Thursday 10th September 2020, 21:00 – Friday 11th September 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Wolverhampton TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

Planned Work: Birmingham TE.

Posted: Wednesday, August 19th, 2020 at 15:45 by Iain Beveridge

Thursday 3rd September 2020, 21:00 – Friday 4th September 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Birmingham TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

  1. Naz says:

    Work is now commencing

  2. Naz says:

    Work has been completed