Archive for February 9th, 2021

Emergency Work: London Interxion Suite (LON44)

Posted: Tuesday, February 9th, 2021 at 19:45 by Iain Beveridge

Tuesday 09th February 2021, 22:00 – Wednesday 10th February 2021 05:00

During the above window, we will be working to restore power stability to some PWAN infrastructure and customer firewalls within our interxion suite. An ATS that is supplying one of out racks is faulty, we will be moving devices and config one at a time to new infrastructure within another rack in the suite. There will be a small window of downtime as we move these devices one at a time in a staged and controlled manner.

  1. Bogdan Voda says:

    Please be aware the above works is now about to commence.

  2. Bogdan Voda says:

    This has now been completed for tonight.
    Further work will need to be completed out of hours and will be communicated in due course.

    Apologies for the short notice and any inconvenience this may cause.