Archive for August, 2020

Planned Work: Milton Keynes POP

Posted: Wednesday, August 26th, 2020 at 10:01 by Iain Beveridge

Thursday 1st October 2020, 21:00 – Friday 2nd October 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Milton Keynes TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

Planned Work: Milton Keynes POP

Posted: Wednesday, August 26th, 2020 at 09:59 by Iain Beveridge

Thursday 24th September 2020, 21:00 – Friday 25th September 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Milton Keynes TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

Emergency Work: Cardiff POP

Posted: Tuesday, August 25th, 2020 at 15:08 by Iain Beveridge

Friday 28th August 2020, 00:00 – 02:00

After a power check within Cardiff POP, BT identified an issue with part of the power infrastructure within one of our racks.

Therefore, BT will be undertaking emergency maintenance work in the above window whilst a UPS is swapped within the rack. The core network router is not in this rack and not expected to experience any loss of service, customers with circuits terminating in Cardiff BT POP should be considered at risk only as the work should be able to be completed with no disruption to service.

  1. Robin Posadas says:

    Work now commencing.

  2. Robin Posadas says:

    Work now completed.

Planned Work: Wolverhampton POP

Posted: Wednesday, August 19th, 2020 at 16:01 by Iain Beveridge

Thursday 17th September 2020, 21:00 – Friday 18th September 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Wolverhampton TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

  1. Naz says:

    work is now commencing

  2. Naz says:

    Work is now completed

Planned Work: Wolverhampton POP

Posted: Wednesday, August 19th, 2020 at 15:47 by Iain Beveridge

Thursday 10th September 2020, 21:00 – Friday 11th September 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Wolverhampton TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

Planned Work: Birmingham TE.

Posted: Wednesday, August 19th, 2020 at 15:45 by Iain Beveridge

Thursday 3rd September 2020, 21:00 – Friday 4th September 2020 05:00

Due to on going improvements to the power infrastructure within the BT POP’s, Birmingham TE requires both the ATS and UPS to be refreshed.

Therefore, BT will be undertaking maintenance work within the above window which will require the power feeds to be moved, whilst an ATS & UPS are swapped within the rack. Although the core network router is not expected to experience any loss of service, customers connecting into the adjacent equipment will experience a small period of downtime.

  1. Naz says:

    Work is now commencing

  2. Naz says:

    Work has been completed

Emergency Work: Peterborough BT POP.

Posted: Tuesday, August 18th, 2020 at 17:27 by Iain Beveridge

Wednesday 19th August 2020, 00:00 – 03:00

After a power check within Peterborough POP, BT identified an issue with part of the power infrastructure within one of our racks.

Therefore, BT will be undertaking emergency maintenance work in the above window whilst a UPS is swapped within the rack. The core network router is not in this rack and not expected to experience any loss of service, customers with circuits terminating in Peterborough BT POP should be considered at risk only as the work should be able to be completed with no disruption.

  1. Naz says:

    work is now commencing

  2. Naz says:

    work is now completed

Lon50/Telecity-hex89.core device outage

Posted: Tuesday, August 18th, 2020 at 05:20 by Adam Heath

Our Co-Location provider for this site has advised of a power outage which is effecting multiple floors within the London Harbour Exchange building. Investigations are being carried out to determine an RCA. At the time of this post the building has been evacuated due to the fire alarm triggering.

More information to be provided as and when we have updates from our Co-Location provider

  1. ljordan says:

    Further updates pending but Talk Talk are currently invesigating further. As soon as they are made available we will advise further.

  2. ljordan says:

    We are still awaiting further updates from the suppliers on this outage. The London building is also still under evacuation. The engineers are on site to investigate as soon as possible. As soon as we have any news, we will advise further.

  3. ljordan says:

    It been advised by Equinix that there is multiple core links experiencing an outage and 36 network to network interface ports causing Business customers connected to the London Harbour and Harbour exchanges to experience a Total Loss of Service. Outage start time was 04:23 (18/08). Full Impact assessment is still ongoing.

    Latest Update
    Equinix have advised that a fire alarm was triggered by the failure of output static switch from their Galaxy UPS system. This has resulted in a loss of power for multiple customers and Equinix IBX Engineers are working to resolve the issue

  4. mpurcell says:

    Latest Update:

    Engineers from Equinix continue to work on restoring power at the datacentre to restore service.

    Escalations have been made to suppliers who hand over services to us at this location with a view of getting more detail and timescales from Equinix. Equinix IBX site staff reports that IBX engineers and the specialist vendor have begun restoring services to customers by migrating to newly installed and commissioned infrastructure. IBX engineers continue to work towards restoring service to all customers

    Root cause has not currently been identified.

    Next update expected at 1000

  5. mpurcell says:

    Update is due shortly. Will update here as soon as it is received.

  6. mpurcell says:

    Latest Update:

    Talk Talk Support Teams have confirmed that services remain impacted but IBX staff are being allowed back on site and have confirmed that the fire detection system has been fully restored. The Galaxy UPS failure remains an ongoing incident and is currently under investigation

  7. mpurcell says:

    Latest Update:

    Equinix Engineers have advised that their IBX team have begun restoring power to affected devices. Unfortunately, at present there remains no estimate resolution time.

    We will continue to provide updates as soon as they come through.

  8. mpurcell says:

    Latest Update:

    Equinix IBX staff have reported that some services have been reinstated and they continue to work towards restoring services to all customers by migrating to the newly installed and commissioned infrastructure. Talk Talk Network teams have also confirmed that some 3rd party services are coming back online.

  9. mpurcell says:

    Latest Update:

    Equinix IBX Site Staff reports that services have been further restored for several more customers and IBX Engineers continue to work towards restoring services to all customers by migrating to the newly installed and commissioned infrastructure

  10. mpurcell says:

    Apologies, no further updates at present. As soon as one comes through we will update here.

  11. mpurcell says:

    Latest Update:

    Equinix IBX Site Staff reports that services have been further restored to more customers and increasing numbers of those affected are now operational along with the majority of Equinix Network Services. IBX Engineers continue to work towards restoring services to all customers by migrating to the newly installed and commissioned infrastructure.

    No root cause has yet been identified.

  12. mpurcell says:

    Latest Update:

    Internally we are beginning to see an increasing number of our services coming back online.

  13. mpurcell says:

    Latest Update:

    Talk Talk reports that Service was restored at 15:36 to the TalkTalk switch, in HEX, on the Legacy TUK Network.

    IBX Engineers continue to work towards restoring services to all customers by migrating to the newly installed and commissioned infrastructure and estimate full restoration by or before 21:00 GMT/BST.

  14. mpurcell says:

    Additional to last:

    Equinix have advised that electrical work is being carried out at the data centre whereby services (under floor sockets) require migration to a new distribution board as one has failed. There are 8 floors that require this work to be carried out. Floors one and two have been completed. As a result we still consider the services to be at risk, despite them being restored currently. Further outages may be seen until the expected completion time of 21:00hrs tonight.

  15. ljordan says:

    Latest Update
    Equinix IBX Site Staff reports that restoration of services continues. The remaining affected customers are in the process of being migrated to the newly installed and commissioned infrastructure. A revised resolution time has not yet been provided.

  16. ljordan says:

    Equinix advised that all services are now restored. All customers are now fed from the new infrastructure and at full redundancy. UPS failure was deemed the cause. The incident will now be resolved as all systems are available with no further issues reported. Monitoring will remain in place to ensure stability.

Emergency Work: Glasgow POP

Posted: Monday, August 17th, 2020 at 14:04 by Iain Beveridge

Tuesday 17th August 2020, 00:00 – 03:00

After a power check within Glasgow POP, BT identified an issue with part of the power infrastructure within one of our racks.

Therefore, BT will be undertaking emergency maintenance work in the above window which will require the power feeds to be moved, whilst an ATS & UPS is swapped within the rack. The core network router is not in this rack and not expected to experience any loss of service, customers with BT EAD circuits terminating in Glasgow should be considered at risk.

  1. Naz says:

    work is now commencing

  2. Naz says:

    work now completed

Incident: BT Edinburgh

Posted: Wednesday, August 12th, 2020 at 08:57 by David Brewis

A major incident has been declared by BT for an exchange in Edinburgh impacting broadband and ethernet services.

Loss of service is a result of water ingress into the location. The emergency command centre is onsite with majority of water removed, with engineers ensuring safe to enter to continue investigations and restore services as soon as possible.

Further updates will be provided.

  1. David Brewis says:

    Engineers remain on site with a plan in place, working to attempt to restore service. Equipment continues to remove remaining water with spare hardware and cabling on site and on route.

    Next update to follow by 13:30

  2. David Brewis says:

    Water has been removed from the building and clean up is in progress. Cables have been reconnected providing restoration steps with testing being carried out.

    Works will continue on site ensuring the location is secure and no further risk.

    Next update to follow by 15:30

  3. David Brewis says:

    Sessions appear to have returned from around 13:30 and we will continue to monitor our network equipment and the progress of clean up activities.

    No further updates to follow unless further disruption is caused by these activities as the incident is now resolved. If you experience a loss of service please call into the helpdesk following a reboot of your equipment.